How we cut rework by 61% at a construction company with BIM 5D

01 / The company

The company

The company is a construction firm that builds mid-size and large residential, commercial and industrial projects. It runs 8 to 12 projects at the same time, at different stages, with around 600 direct employees and 1,200 contractors.

In an operation of this size, the integration between design, budget and construction defines the cost, the schedule and the quality of each project. It was to give structure to this integration that the company began its partnership with NextAge.

02 / The challenge

Integrating design, budget and construction

Tired professional in an office, with a hand on her forehead and her glasses in the other hand

The design, budget and construction teams worked in silos, which led to recurring budget overruns. Clashes between complementary designs caused rework, which accounted for 12% of total costs. With 8 to 12 projects underway, consolidating the data from each site was hard, and decisions were slow.

So the challenge was not just adopting a new design tool. It was connecting the model, the cost and the schedule of each project in a single base, to detect problems before construction and give management a consolidated view of every site.

3D model

Every element of the model is linked to unit costs, suppliers and deadlines.

Easy clash detection

The system automatically identifies clashes between design disciplines before construction begins.

Physical progress straight from the site

A mobile module lets engineers update construction progress directly from the site.

Want to bring this technology to your company?

Discover our software factory

A key part of the project was linking every element of the 3D model to unit costs, suppliers and deadlines, and automatically detecting clashes between disciplines before construction.

This allowed the company to anticipate clashes and overruns while still in design, instead of fixing them on site, and to track the physical progress of each project with the same data behind the budget and the schedule.

BIM 5D platform on a laptop, with a project dashboard, schedule and costs, and the mobile app on a phone

04 / The result

The result

The platform now connects design, budget and construction in a single base. The company gained cost predictability, started catching clashes before construction and now makes decisions with consolidated data from all its projects.

Design, budget and schedule connected. Every element accounts for costs and deadlines.

Clashes between disciplines identified before construction.

Physical progress updated in real time, giving management a view of every project.

What's more...

61%

less rework from design clashes

38%

fewer budget overruns

With NextAge, the company stopped discovering clashes on site and started catching them before construction.

Learn more about how we help the civil construction sector

Visit our page about the civil construction sector

Let's talk

Get in touch with one of our specialists:

Smiling professional in a black blazer working on a laptop